Solved

When a Manager Does Not Accept a Positive NPV Project,shareholders

Question 109

Multiple Choice

When a manager does not accept a positive NPV project,shareholders face an opportunity cost in the amount of the:


A) project's initial cost.
B) project's NPV.
C) project's discounted cash flows.
D) soft capital rationing budget.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge