How does net working capital affect the NPV of a 5-year project if working capital is expected to increase by $25,000 and the firm has a 15% cost of capital?
A) NPV will increase by $9,322.
B) NPV will increase by $12,571.
C) NPV will decrease by $25,000.
D) NPV will decrease by $12,571.