    A Hierarchical Listing of What Must Be Done in a Project
Solved

A Hierarchical Listing of What Must Be Done in a Project

Question 112

Question 112

Multiple Choice

A hierarchical listing of what must be done in a project is called:


A) work breakdown structure (WBS)
B) PERT
C) planning matrix
D) crashing
E) critical path

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q15: A Gantt chart is built using established

Q20: Gantt charts are most closely associated with<br>A)JIT.<br>B)PERT.<br>C)MRP.<br>D)MRPII.<br>E)Six

Q28: The probability of occurrence of risk events

Q107: Determine the amount of slack in each

Q108: Using the information given in the following

Q109: What is the probability that this project

Q110: What is the probability that this project

Q115: What is the probability that the critical

Q116: Once a project is underway, the project

Q116: In PERT, the expected project duration will

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines