In the Project Network Presented Below, Numbers on Each Arrow

Question 29

Essay

In the project network presented below, numbers on each arrow refer to the expected time and standard deviation in weeks for that particular activity.For example, "8,2" indicates an activity with an expected time of 8 and a standard deviation of two weeks.

Correct Answer:

verifed

Verified

blured image For this project, determine each of the...