Multiple Choice
What is the estimated expected (mean) time for project completion?
A) 41 days
B) 70 days
C) 100 days
D) 120 days
E) 221 days
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q4: If two consecutive activities have shared slack,
Q10: In order to determine the probability of
Q12: The path in a network with the
Q39: The sum of times of the longest
Q50: The earliest finish time for an activity
Q59: Project managers are sometimes able to reduce
Q62: What is the estimated expected (mean) time
Q63: What are the estimated slack times (in
Q64: What is the estimated standard deviation in
Q87: Which of the following is not an