menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Operations Management Study Set 1
  4. Exam
    Exam 17: Project Management
  5. Question
    What Is the Probability That the Critical Path for This
Solved

What Is the Probability That the Critical Path for This

Question 5

Question 5

Multiple Choice

What is the probability that the critical path for this project will be completed within 210 days?


A) 0.5000
B) 0.8413
C) 0.9544
D) 0.9772
E) 0.9987

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q1: What is the estimated expected (mean) time

Q6: What is the estimated expected (mean) time

Q7: Simulation can be used for cases in

Q8: What is the estimated slack time for

Q10: What is the estimated expected (mean) time

Q20: Although PERT and CPM were originally developed

Q27: Activity J has a duration of 7

Q64: A popular tool for planning and scheduling

Q114: Matrix organizations transfer control of workers to

Q118: The basis for use of the beta

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines