menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Operations Management Study Set 1
  4. Exam
    Exam 17: Project Management
  5. Question
    What Is the Probability That the Critical Path for This
Solved

What Is the Probability That the Critical Path for This

Question 102

Question 102

Multiple Choice

What is the probability that the critical path for this project will be completed within 52 weeks?


A) 0.1554
B) 0.3108
C) 0.3466
D) 0.6554
E) 0.8277

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q13: Which of the following are advantages of

Q36: Slack time is equal to LS-ES or

Q63: Most likely time generally is more than

Q66: The network diagram describes sequential relationships among

Q74: The project management strategy of injecting additional

Q97: If an activity is determined to be

Q98: In PERT, the path with the fewest

Q104: What is the probability that this project

Q105: A project has the activities and activity

Q107: Determine the amount of slack in each

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines