Multiple Choice
What is the probability that the critical path for this project will be completed within 52 weeks?
A) 0.1554
B) 0.3108
C) 0.3466
D) 0.6554
E) 0.8277
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q13: Which of the following are advantages of
Q36: Slack time is equal to LS-ES or
Q63: Most likely time generally is more than
Q66: The network diagram describes sequential relationships among
Q74: The project management strategy of injecting additional
Q97: If an activity is determined to be
Q98: In PERT, the path with the fewest
Q104: What is the probability that this project
Q105: A project has the activities and activity
Q107: Determine the amount of slack in each