The Two Different Approaches to Load Work Centers in Job-Shop

Question 14

Multiple Choice

The two different approaches to load work centers in job-shop scheduling are:


A) load charts and schedule charts
B) Gantt charts and assignment method
C) infinite loading and finite loading
D) linear programming and makespan
E) none of the above