Multiple Choice
The two different approaches to load work centers in job-shop scheduling are:
A) load charts and schedule charts
B) Gantt charts and assignment method
C) infinite loading and finite loading
D) linear programming and makespan
E) none of the above
Correct Answer:

Verified
Correct Answer:
Verified