Multiple Choice
If he uses the earliest due date first (EDD) priority rule to schedule these jobs, what will be the average job tardiness?
A) 0 hours
B) 1.5 hours
C) 1.75 hours
D) 2 hours
E) 2.25 hours
Correct Answer:

Verified
Correct Answer:
Verified