Multiple Choice
If Eva uses the earliest due date first (EDD) priority rule to schedule these jobs, what will be the average job tardiness?
A) 2 hours
B) 2.2 hours
C) 2.33 hours
D) 2.4 hours
E) 3 hours
Correct Answer:

Verified
Correct Answer:
Verified