If Eva Uses the Shortest Processing Time First (SPT) Priority

Question 92

Multiple Choice

If Eva uses the shortest processing time first (SPT) priority rule to schedule these jobs, what will be the average completion time?


A) 3 hours
B) 5 hours
C) 7 hours
D) 7.2 hours
E) 8 hours