Net requirements for component J are as follows: 60 units in week 2, 40 units in week 3, and 60 units in week 5.If a fixed-period, three-period lot-sizing method is used, what will be the quantity of the first planned receipt?
A) 60
B) 100
C) 160
D) Cannot be determined
E) None of the above
Correct Answer: