Multiple Choice
Which of the following would not be a strategy associated with adjusting aggregate capacity to meet expected demand?
A) subcontract
B) vary the size of the workforce
C) vary the intensity of workforce utilization
D) allow inventory levels to vary
E) use backorders
Correct Answer:

Verified
Correct Answer:
Verified