Multiple Choice
Moving from the aggregate plan to a master production schedule requires
A) rough-cut capacity planning.
B) disaggregation.
C) suboptimization.
D) strategy formulation.
E) chase strategies.
Correct Answer:

Verified
Correct Answer:
Verified