A master production schedule quantity of 300 units will arrive in week 6.Weekly demand over weeks 3 through 10 is forecasted at 50 units.At present, orders have been booked in various quantities in weeks 1, 2, 3 and 4.What is the available to promise for week 6?


A) 50
B) 6
C) 300
D) 100