Multiple Choice
Which of the following steps is necessary to ensure that a master schedule is valid?
A) worker scheduling
B) order promising
C) inventory counting
D) order booking
E) rough-cut capacity planning
Correct Answer:

Verified
Correct Answer:
Verified