Multiple Choice
If he uses an acceptance sampling plan of n = 20 and c = 1, what will be the average outgoing quality (AOQ) for batches with 15% defectives?
A) 0.0263
B) 0.1237
C) 0.1756
D) 0.8244
E) 0.9737
Correct Answer:

Verified
Correct Answer:
Verified