Multiple Choice
When a process is in control, it results in there being, on average, 16 defects per unit of output.C-chart limits of 8 and 24 would lead to a _______ chance of a Type I error.
A) 67%
B) 92%
C) 33%
D) .03%
E) 5%
Correct Answer: