A Manager Is Trying to Estimate the Learning Rate for a New

Question 62

Multiple Choice

A manager is trying to estimate the learning rate for a new job.The first unit took 16 hours and the fourth unit required about 13 hours.The learning rate is:


A) 70%
B) 75%
C) 80%
D) 85%
E) 90%