Question 37

Essay

The 3rd unit of a ten-unit job required 7.3 hours to complete.The 4th unit has been worked on for two hours, but it is not yet finished.Estimate the remaining amount of time that will be needed to finish this ten-unit job if the work has an 80% learning curve.

Correct Answer:

verifed

Verified

We will need 37.66 h...