    What Is the Normal Time (NT) for This Task If
Solved

What Is the Normal Time (NT) for This Task If

Question 23

Question 23

Multiple Choice

What is the normal time (NT) for this task if the employee worked at a fifty-percent faster pace than is average?


A) 45 seconds
B) 60 seconds
C) 90 seconds
D) 135 seconds
E) 180 seconds

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q18: What is the standard time (ST) for

Q21: Management compensation should be based primarily on

Q26: For a confidence level of 95.44% and

Q27: What is the observed time (OT) for

Q28: If the person observed worked at a

Q32: When performing a time study, the analyst

Q82: Job enrichment involves giving a workers a

Q85: The technique which can be used to

Q126: A disadvantage of teams is:<br>A)higher quality.<br>B)higher productivity.<br>C)greater

Q133: What is the effect of an increase

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines