Multiple Choice
What is the standard time (ST) for this task if the employee worked at a fifty-percent faster pace than is average, and an allowance of twenty percent of job time is used?
A) 90 seconds
B) 99 seconds
C) 100 seconds
D) 162 seconds
E) 150 seconds
Correct Answer: