Multiple Choice
What is the standard time (ST) for this task if the employee worked at a fifty-percent faster pace than is average, and an allowance of ten percent of the workday is used?
A) 90 seconds
B) 99 seconds
C) 100 seconds
D) 168.8 seconds
E) 150 seconds
Correct Answer:

Verified
Correct Answer:
Verified