Multiple Choice
What is the standard time (ST) for this task if the employee worked at a 20% faster pace than is average and an allowance of 25% of the workday is used?
A) 40 seconds
B) 50 seconds
C) 53.3 seconds
D) 60 seconds
E) 64 seconds
Correct Answer:

Verified
Correct Answer:
Verified