Multiple Choice
A production line is to be designed for a job with three tasks.The task times are 0.4 minutes, 1.2 minutes, and 0.5 minutes.The maximum cycle time in minutes is:
A) 0.3
B) 0.7
C) 1.4
D) 2.1
E) 0.8
Correct Answer:

Verified
Correct Answer:
Verified
Q67: An idle percentage of zero means a
Q74: Process layouts feature departments or other functional
Q84: "Balance delay" is another name for the
Q125: What is the layout that will minimize
Q126: Given the following data:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2514/.jpg" alt="Given the
Q127: For output to equal projected demand, what
Q128: Which of the following is not a
Q130: Flexible manufacturing systems (FMS) bring the benefits
Q132: For output to equal projected demand, what
Q134: Computer-aided manufacturing (CAM) refers to the use