Operation X feeds into Operation Y.Operation X has an effective capacity of 55 units per hour.Operation Y has an effective capacity of 50 units per hour.Increasing X's effective capacity to ensure that Y's utilization is maximized would be an example of ________ a constraint.
A) overcoming
B) outsourcing
C) insourcing
D) cushioning
E) none of the above