In an Assembly Operation at a Furniture Factory, Six Employees

Question 19

Multiple Choice

In an assembly operation at a furniture factory, six employees assembled an average of 450 standard dining chairs per 5-day week.What is the labor productivity of this operation?


A) 90 chairs/worker/day
B) 20 chairs/worker/day
C) 15 chairs/worker/day
D) 75 chairs/worker/day
E) none of the above