Multiple Choice
During which of the following phase gates would the question of "Are time, costs, and scope performances within acceptable limits?" be answered?
A) Proposal
B) Screening and selection
C) Implementation
D) Progress evaluation
E) Closure
Correct Answer:

Verified
Correct Answer:
Verified