Short Answer
"Go, Kill, Hold, or Recycle" decisions are made by the oversight team at each _________ of a project.
G.Cooper several decades ago to improve management of new-product development.The original model incorporates five stages: preliminary investigation, detailed investigation, development, testing and validation, and full production and market launch.Stages precede gates and represent information developed to enable gatekeepers to make the right decision at the next gate.These decision points at each gate are known as go, kill, hold, or recycle decisions.Given the information developed for each stage, the gatekeepers (the oversight team) can decide to continue with the project, abort the project, or revise/recycle.
Correct Answer:

Verified
phase gate
Explanati...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
Explanati...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q39: Which of the following is not one
Q40: Portfolio Project Management is responsible for the
Q41: The Proposal phase answers the fundamental question:
Q42: During which of the following phase gates
Q43: The appearance of a project office frequently
Q45: During which of the following phase gates
Q46: The importance of the increase in project
Q47: The phase gate methodology was developed before
Q48: The _ is responsible for the continued
Q49: Organizational options to cover every aspect of