True/False
The decision points at each phase gate are known as "Go, Kill, Hold, or Recycle" decisions.
G.Cooper several decades ago to improve management of new-product development.The original model incorporates five stages: preliminary investigation, detailed investigation, development, testing and validation, and full production and market launch.Stages precede gates and represent information developed to enable gatekeepers to make the right decision at the next gate.These decision points at each gate are known as go, kill, hold, or recycle decisions.Given the information developed for each stage, the gatekeepers (the oversight team) can decide to continue with the project, abort the project, or revise/recycle.
Correct Answer:

Verified
Correct Answer:
Verified
Q55: The original Stage-Gate<sup>TM</sup> model included all the
Q56: It is extremely rare that a project
Q57: Phase 1 of the abridged, generic phase
Q58: During which of the following phase gates
Q59: What is Phase Gate Methodology and what
Q61: An informal culture that values improvement drives
Q62: The first phase of the generic phase
Q63: Typical activities of project oversight cover which
Q64: Level 3 of the authors' Project Maturity
Q65: Phase 2 of the abridged, generic phase