Multiple Choice
When the project may be completed early with some parts of the project eliminated this is considered to be ___________ closure.
A) Normal
B) Premature
C) Perpetual
D) Changed Priority
E) Failed Project
Correct Answer:

Verified
Correct Answer:
Verified