Implementing closedown includes the following major activities except:
A) Getting delivery acceptance from the customer.
B) Shutting down resources and releasing to new uses.
C) Closing accounts and seeing all bills are paid.
D) E-mail the project team that the project is complete.
E) Creating a final report.