Multiple Choice
The second step in the project control process of the measurement and evaluation of project performance is to:
A) Review the baseline plan with top management
B) Analyze inputs to control system
C) Compare plan against actual
D) Measure progress and performance
E) Review spending with team members
Correct Answer:

Verified
Correct Answer:
Verified