Multiple Choice
he earned value of a project is the:
A) Project cost to date adjusted for project scope changes
B) Total project cost to date
C) Cost incurred minus the planned cost
D) Percent of the original budget that has been earned by actual work
E) None of these are correct
Correct Answer:

Verified
Correct Answer:
Verified
Q2: A CPI index of 0.97 indicates that
Q26: Identify the four indexes used in project
Q28: Scope creep affects:<br>A)The organization<br>B)The project team<br>C)The project
Q29: Generally the method for measuring accomplishments centers
Q30: The cost variance for a project is
Q32: Which of the following will calculate the
Q33: Overhead costs and profit are typically included
Q34: What is scope creep and why should
Q36: A positive variance in SV or CV
Q43: _ holds people accountable, prevents small problems