Multiple Choice
The optimum duration for a project is at the point where:
A) Direct costs are the lowest
B) Indirect costs are the lowest
C) Direct costs equal indirect costs
D) Total project costs are the lowest
E) The project changes from time-constrained to resource-constrained
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q10: Costs such as labor, materials, equipment, or
Q34: The _ time for an activity represents
Q41: The accuracy of crash times and costs
Q51: In the "I'll Bet You..." Snapshot from
Q52: Total project costs include all of the
Q55: The relationship between cost and time for
Q56: The _ project cost is the sum
Q56: Shortening an activity is called _.
Q58: Expected time for an activity represents low-cost,
Q79: How would you calculate an activity's slope