Short Answer
Because direct costs are assumed to be developed from normal methods and time, any reduction in activity time should ________ the cost of the activity.
Correct Answer:

Verified
increase
Explanation: Because ...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
increase
Explanation: Because ...