According to ________, adding more manpower to a late software project makes it later.

Correct Answer:

verifed

Verified

Brooks' law
Explanat...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q34: The _ time for an activity represents

Q56: Shortening an activity is called _.

Q58: Expected time for an activity represents low-cost,

Q60: _ is probably the most common response

Q62: The easiest way to add more labor

Q63: A common method for shortening the project

Q65: Identify and briefly describe five reasons for

Q66: Cost slope can be determined by dividing

Q79: How would you calculate an activity's slope

Q82: Managers have several effective methods for crashing

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines