Multiple Choice
Sam is trying to order the concrete needed to continue his project.However, the supplier won't be able to deliver it until next week.This is an example of a _______ constraint.
A) Working capital
B) People
C) Equipment
D) Information
E) Materials
Correct Answer:

Verified
Correct Answer:
Verified