Multiple Choice
In reviewing the status of her project with top management, Shirley was told that there only were two programmers that she could use for her project.Her project is __________ constrained.
A) Time
B) Quality
C) Cost
D) Performance
E) Resource
Correct Answer:

Verified
Correct Answer:
Verified