Multiple Choice
Jan is trying to reallocate resources in a time-constrained project to create smoother resource utilization with a low level of risk.She should move to activities with the
A) Smallest duration
B) Least slack
C) Most slack
D) Lowest identification number
E) Highest cost
Correct Answer:

Verified
Correct Answer:
Verified