Multiple Choice
Splitting an activity creates the following situation:
A) More people working on the same activity
B) There are possible startup and shutdown costs
C) A resource may be moved from one activity to another and then back
D) Both B and C are correct
E) A, B, and C are all correct
Correct Answer:

Verified
Correct Answer:
Verified