A project budget report is showing our project as spending $35,000 against a budgeted amount of $40,000.Which of the following is true?
A) We are spending less than we should for the project
B) We are doing a good job managing the project
C) We should check to see if all the bills have been paid
D) Both A and B are correct
E) We can't be sure how the project is going