    Exam 8: Scheduling Resources and Costs
  5. Question
    Having One Person Responsible for Performing Several Activities, All Due
Solved

Having One Person Responsible for Performing Several Activities, All Due

Question 92

Question 92

Short Answer

Having one person responsible for performing several activities, all due at the same time, is an example of a(n)________ constraint.

Correct Answer:

verifed

Verified

resource
Explanation: If one p...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q21: Comparing Planned Costs versus Actual Costs will

Q72: Why is a schedule not a schedule

Q79: List and briefly describe the disadvantages of

Q81: Resource dependency takes priority over technological dependency

Q88: A project cost baseline is also called

Q90: Most of the scheduling methods available today

Q91: The inability to fit more than two

Q93: All leveling techniques delay noncritical activities by

Q94: In a resource-constrained project the second priority

Q95: Delaying noncritical activities to lower peak demand

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines