Multiple Choice
Funds that are for identified risks that have a low probability of occurring and that decrease as the project progresses are called ______ reserves.
A) Management
B) Budget
C) Contingency
D) Padded
E) Just in case
Correct Answer:

Verified
Correct Answer:
Verified