The forward pass in project network calculations determines the
A) Earliest time's activities can begin
B) Earliest time's activities can be finished
C) Duration of the project
D) Both A and B are correct
E) A, B, and C are all correct
Correct Answer:

Verified
Correct Answer:
Verified