Question 45

Multiple Choice

Ed is looking over the actual results of projects and comparing them to what was estimated.He notices that projects that took six months or longer to complete were noticeably more off the estimates.Which of the following factors is he recognizing?


A) Padding estimates
B) Planning horizon
C) Project structure
D) People
E) Organization culture