Multiple Choice
Jose is forecasting project time and cost for constructing a new building by multiplying the total square footage by a given dollar amount.Which of the following methods is he using?
A) Ratio
B) Template
C) Apportion
D) Function point
E) Learning curve
Correct Answer:

Verified
Correct Answer:
Verified
Q8: The ideal approach to estimating project time
Q48: The consensus method of estimating costs is
Q61: Costs that are associated with time devoted
Q62: Which of the following is NOT one
Q64: A way to improve estimates on future
Q68: The top-down method for estimating project time
Q69: Benefits of Reference Class Forecasting include<br>A)Acting as
Q71: General and administrative costs are usually allocated
Q71: The salary of the project manager and
Q81: Under what conditions would the top-down approach