Multiple Choice
The bottom-up approach for estimating times and costs that uses costs from past projects that were similar to the current project is known as
A) Detailed WBS work package estimates.
B) Template method.
C) Function point method.
D) Time-phased cost estimates.
E) Phase estimating.
Correct Answer:

Verified
Correct Answer:
Verified