Multiple Choice
Which of the follow top-down methods is used when projects closely follow past projects in features and costs and result in costs being assigned by percentages to major segments of the project?
A) Apportion
B) Function point
C) Phase estimating
D) Learning curve
E) Consensus
Correct Answer:

Verified
Correct Answer:
Verified