Which of the Follow Top-Down Methods Is Used When Projects

Question 81

Multiple Choice

Which of the follow top-down methods is used when projects closely follow past projects in features and costs and result in costs being assigned by percentages to major segments of the project?


A) Apportion
B) Function point
C) Phase estimating
D) Learning curve
E) Consensus