The Tendency to Over-Estimate Project Time and Cost in Order

Question 52

Short Answer

The tendency to over-estimate project time and cost in order to improve the likelihood of meeting the estimates is known as the ________ factor.

Correct Answer:

verifed

Verified

padding estimates
Explanation: In work s...